Hi Arnold,



I’ve tried doin the global change but it really doesn’t work but I would be glad if you can teach me the workaround. I agree that P6 made it easier by filtering activities with the activity codes assigned, and use the command bar for assigning resources.



Thanks,



RJ

K
Kieran Thomson 👤 Member for 22 years 4 months

Dude, why change the activity code for something it’s not to be. Play along with your bean counters. If you need to re-filter go along the lines of something else!

Any more departmental crap and tel them your only the brains.... not the mastermind!

P
pat Gatus 👤 Member for 16 years 9 months

Hi arnold,



First of all thank you, hey arnold i would like to explain to you my vision.what i want to do is assign a certain activity code in my list of activities for example i have an activity excavation i like to assign an activity code to that activity lets say 022020 is my activity doce assigned. then in the global change feature i like to say to P6 that all activities assigned with an activity code of 022020 assign resources to that activity such as foreman laborer and a helper... do you think it is possible?



thanks

R
RJ Rivera 👤 Member for 21 years 9 months

Hi Arnold,



Maybe I’ll try upgrading my version, im using 6.1, will try upgrading it to V7.





Thanks,



RJ

A
Arnold Puy 👤 Member for 19 years 1 month

Hi RJ,



I tried this but it’s working fine with me. I am using P6 v.6.2.1 before and now P6 v7.0





Regards,



Arnold

R
RJ Rivera 👤 Member for 21 years 9 months

Hi Arnold,



What he really want is to assign resources using global change to activities with specific activity codes assigned on it, as far as I know this is still an enhancement request, and I am not sure if this has been resolved in P6 v7.



I also agree it is much easier to filter activities and use the resource tab in the command bar for assigning resources.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Pat,



I got what you mean.. The reason why you cannot use this Subject Area that fit your requirements it is because, some Parameters & Value is not available from Activities, Resource Assignment & Project Expenses.



Try to use the easy functionality in the Navigation Bar, Activity Toolbar, Directory & Command Bar Button.





Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts