Shah. HB 👤 Member for 17 years 6 months

There are few functions in global change option that would help you to modify the existing activity IDs as i posted in last message

R
Ronald Romero 👤 Member for 19 years 6 months

Hi Dinesh,



P3/P6 dont have the facilities using global change to auto increment Activity ID. The easiest way is to export it to other software like excel then import back again. Excel has robust facilities in changing text and integers including automatic renumberingincluding the formula like concactenate .





Hope this this provide solution.



Regards,



Ronald

S
Shah. HB 👤 Member for 17 years 6 months

Any clarificaiton of global change functions you could post on this thread so that seniors out here will get you better solution

S
Shah. HB 👤 Member for 17 years 6 months

Hi dinesh you could modify your activity ID in P3 using global change ,check out in help {P3} and search for global change you might come across list of functions like RIGHT,LEFT and so on which would help you to modify your activity ID in easy way out

S
Shah. HB 👤 Member for 17 years 6 months

Yes there is a way out in global change .I will get back soon

D
Dinesh Kumar 👤 Member for 20 years 1 month

In fact, When I was done with my schedule, Client came up with an activity ID coding system. So now I’m forced to change all the activity IDs (about 1000 of them in number) to suit. Is there a way out for this with a Global change?

S
Shah. HB 👤 Member for 17 years 6 months

Dinesh ,you need to increment a activity through global change option?

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts