my mistake!"Remaining work" field does not exist in the Task Usage or Resource Usage details
and it is not possible to use a custom field instead
the only way to distribute the remaining work across the project duration is to export the data to Excel by using either File, Save As, Excel crosstab or MS Projects new Visual Reports
Right click in the right hand pane of the screen, and select Remaining Work in the pop up menu; or select Details and set up the fields in a particular order from top to bottom
I would like to see it spread out over the project. In the columns to the rights. What I do now is subtract Actual Work from Work and that gives you the remaining work. The problem with this is that I have to do everything via excel witch leaves me vulnerable for mistakes.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
I do use the schedule for cost. Thanks for that tip
...and change the column heading for "Cost" to "Remaining Work".
rgds,
Bo
Willem,
There is one way of doing it, although it is not "nice".
If you do not cost load your programme, i.e. the cost fields are empty, you can do like the following in the Task Usage view:
1) Introduce "Number1" being customized to "([Work]-[Actual Work])/60", also calculating for summaries
2) Copy "Number1" values into "Cost"-column by Paste Speciel / Paste Links
3) Change symbol for currency to "hrs" under Tools / Options / View
This should do the trick.
Regards,
Bo
Willem,
my mistake!"Remaining work" field does not exist in the Task Usage or Resource Usage details
and it is not possible to use a custom field instead
the only way to distribute the remaining work across the project duration is to export the data to Excel by using either File, Save As, Excel crosstab or MS Projects new Visual Reports
Alexandre
I dont have that function. Strange
[email protected] I will mail you back with a screen shot
Willem,
very strange indeed!
are you sure you cannot display the Task Usage screen and right click on the word "Work" in the right hand pane? or double click on it?
Give me your email by Private Mail (click on the gray envelope close to my name) and I will send screen shots to you
Alexandre
2007
Willem,
which version of MS Project are you working with?
Alexandre
Alexandre
That specific option is not available. That is why I take Work and subtract actual work. Please send a screen shot if possible of it.
Regards
Willem and Darren,
"Yes you can" !
Right click in the right hand pane of the screen, and select Remaining Work in the pop up menu; or select Details and set up the fields in a particular order from top to bottom
Alexandre
Willem,
OK Im on the same page as you now, the simple answer is no I dont believe you can.
Unfortunately I think the only option you have is to keep on using Excel to generate the information you require.
Regards,
Darren
I would like to see it spread out over the project. In the columns to the rights. What I do now is subtract Actual Work from Work and that gives you the remaining work. The problem with this is that I have to do everything via excel witch leaves me vulnerable for mistakes.
Hi Willem,
Insert > Column and select Remaining Work from the Field name drop-down menu.
You can customise and alter any view this way.
Regards,
Darren