I don’t believe float will tell you if a predecessor is driving or not. A predecessor might be part of another chain that is defining its float, if in another chain that happens to be in the critical path it will show 0 float but it will not necessarily be the driver of the successor in question.
You might have two activities in tandem none critical, both with the same non 0 float, and the predecessor might be the driver, zero float is not a requirement for a predecessor to be driving.
By the way the Task Drivers view from the Toolbar in MS Project 2007 is unreliable and seems to have bugs. I changed a non driving 0 lag SF relationship to FF and then it became driving, no way.
We are not surprised that you have never hear of the term “slack” as it concerns a CPM relationship. That is because we just made it up! This doesn’t mean that this is a trivial matter, it just proves that you can’t invent a thing until you first invent another thing (or you can’t get there from here.)
Slack is the amount of ‘unused’ time difference between the predecessor and the successor activities. This slack value has nothing to do with the float values or either of the two activities that it relates. It merely indicates how close each predecessor is to becoming the driving relationship for the successor activity.
... Hum, I heard of the term "slack" as related to CPM over 30 years ago, it was on one of the fisrt editions of the book Project Management with CPM and Pert by Moder and Phillips, latter renamed to Project Management With Cpm, Pert and Precedence Diagramming by Joseph J. Moder, Cecil R. Phillips, Edward W. Davis
Remember that Total (Activity) Float as per traditional CPM jorgon is renamed as Total (Task) Slack by MS Project, therefore maybe relationship slack shall be renamed to be relationsip float as per MS Project unique jorgon. Unconsistency rules our trade.
youre right: in MSP 2k, 2002, 2003, you should write a VBA macro to get the information you want; if you are able to retrieve the driving link from the predecessor and the task float, you will satisfy your need
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
From the following link you can download a sample file where you can explore the Task Drivers view error in MS Project.
http://rapidshare.com/files/274278953/Bug_on_drivers_pane.zip
If you find why, let me know, maybe we can get rid of this fly.
Best regards,
Rafael
I don’t believe float will tell you if a predecessor is driving or not. A predecessor might be part of another chain that is defining its float, if in another chain that happens to be in the critical path it will show 0 float but it will not necessarily be the driver of the successor in question.
You might have two activities in tandem none critical, both with the same non 0 float, and the predecessor might be the driver, zero float is not a requirement for a predecessor to be driving.
By the way the Task Drivers view from the Toolbar in MS Project 2007 is unreliable and seems to have bugs. I changed a non driving 0 lag SF relationship to FF and then it became driving, no way.
From : http://scheduleanalyzer.com/sa_long_theory.htm
Slack
We are not surprised that you have never hear of the term “slack” as it concerns a CPM relationship. That is because we just made it up! This doesn’t mean that this is a trivial matter, it just proves that you can’t invent a thing until you first invent another thing (or you can’t get there from here.)
Slack is the amount of ‘unused’ time difference between the predecessor and the successor activities. This slack value has nothing to do with the float values or either of the two activities that it relates. It merely indicates how close each predecessor is to becoming the driving relationship for the successor activity.
... Hum, I heard of the term "slack" as related to CPM over 30 years ago, it was on one of the fisrt editions of the book Project Management with CPM and Pert by Moder and Phillips, latter renamed to Project Management With Cpm, Pert and Precedence Diagramming by Joseph J. Moder, Cecil R. Phillips, Edward W. Davis
Remember that Total (Activity) Float as per traditional CPM jorgon is renamed as Total (Task) Slack by MS Project, therefore maybe relationship slack shall be renamed to be relationsip float as per MS Project unique jorgon. Unconsistency rules our trade.
Best regards,
Rafael
Ok cheers
Bill,
youre right: in MSP 2k, 2002, 2003, you should write a VBA macro to get the information you want; if you are able to retrieve the driving link from the predecessor and the task float, you will satisfy your need
Alexandre
I am using MSP2000 version. Are you saying that this function is not available in this version?
Bill,
this is a new feature in MSP2007
Alexandre