You are welcome.
Thanks again Arnold..Ive wasted a lot of time, thinking how it became -1 TF..
regards,
Cecil
Hi Cecil,
Try to check the finish date.
1. Go to Edit --> User Preferences --> Dates tab, Time, tick Show minutes and select the 12 hour (1:30 PM).
2. Go to Enterprise --> Projects
2. In Projects Detail Tab --> Dates
3. In "Must Finish Date" if you notice the the time is 12:00 AM, change this to 4:00PM or 5:00PM. It depends on the calendar and time you use.
Otherwise, check your finish date. It should be the same with "Must Finish Date especially the time.
Regards,
Arnold