Hi Richu,
Sorry Ill admit first up that I havent reviewed your file and I dont wish to sound condescending, but are you really going down to such granularity with your project controls, that you have to account for a 0.54% delta between your planned and actual progress?
Obviously my comments wont help you find a solution to your problem, but sometimes wasting a day or two trying to get your formula exact isnt really an effective use of time in the grand scheme of things.
Just a thought.
Regards,
Darren
Rafel,
Number1 is the baseline duration in days. It should be 41 instead, i have corrected & still i get the actual progress (56.72%) less than planned progress (57.26%)in the summary bar.
Actual progress= (Actual dur/(Actual dur + Remaining dur))x100
=(35.17/(35.17+26.83))*100
=56.72%
Following is the link of the corrected file
http://rapidshare.com/files/272525538/Project1.mpp.html
Can someone review & let me know where exactly i have gone wrong.
Regards,
Richu
What does number1 stands for? Maybe a value is wrong or transposed, like a 14 instead of a 41?
Best regards,
Rafael