Creating Cost Curves

R
Raj Maurya 👤 Member for 21 years 10 months

You combined two thing in a single question as I understand. If you want 3 month look ahead schedule (Task) to export into excel or you want to export 3 months resource or cost profile (resources or cost data distribution) to make S curve in excel. In first case it is very simple create new filter as per your need then export. In second case after filtering change the view to task usage then export distributed work in excel. In case of only milestones also you can create new filter for 3 months. Hope this will solve your problem.

F
Forum Guest 👤 Member for 17 years 4 months

Hello,

Use any following way to automatically select these particular milestones: put Indicator # n field to YES, MARK the tasks

Create a filter that will consider only those tasks

Create a Export Map with this filter

You could try also the macro "Time distributed data" to export filtered informations into Excel

Regards

Alexandre Faulx-Briole

http://perso.wanadoo.fr/afaulxbriole

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts