Performance % Compl vs. Schedule % Compl
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
The schedule % complete is calculated by (original duration - remaining duration)/original duration. For performance % complete is calculated by earn value / total value.
Hi John,
The Performance % Complete is used to compute earned value and may be based on the Activity % Complete, and also specifies what percentage of the activitys planned worth has been earned so far.
The Schedule % Complete specifies how much of the activitys baseline duration has been completed so far, and also indicates how much of the activity duration should be currently completed, relative to the baseline.
Regards,
Arnold