Project and Resource calendars

M
mike mark 👤 Member for 16 years 11 months
M
Mike Testro 👤 Member for 20 years 6 months

Hi Mike



Whatever software you use if you put a different calendar on a resource to that of the task you will get bizarre results.



If you have the facility tick your resource to follow "calendar as task" and you will have no further problems - even when you change the task calendar.



As Dieter syas - it is all in the manual and help section.



Best regards



Mike Testro

D
Dieter Wambach 👤 Member for 19 years 5 months

Mike



Please put questions more specific.

On your installation dvd or cd’s there is a reference manual. There you’ll find all about calendars and resource assignments.



Calendar: Per resource or per activity - a default value per project for new activities.



Assignments: Units depend on duration type, the default per resource, individual entry possible per day or for the hole assignment. Curve is possible. Some parameter settings for the project must be regarded - under tab "Resources" and "Calculations".



Good information on these items you’ll find in the "Help".



Did you consider to join a training?



Good luck!



Dieter

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts