Construction of District Cooling Plant

A
A D 👤 Member for 19 years
A
A D 👤 Member for 19 years

Here are some more tips in continuation with Shahul’s post:



10. MEP installations



10.1 Pipeworks

10.1.1 Chilled Water Line

10.1.2 Condenser Water Line

10.1.3 Make-up pipes for Cooling Tower



10.2 Equipment Installation Works

10.2.01 Chiller Modules (Show separate WBS for each module. T&C will be done in sequence for each module)

10.2.02 Secondary Pumps

10.2.03 Primary CHW Pumps

10.2.04 Cooling Tower (Show separate WBS for each module in line with Chillers)

10.2.05 Make-up Pumps

10.2.06 Condenser Water Pumps

10.2.07 Blowdown System Works

10.2.08 Air dirt separator

10.2.09 Filtration Pumps

10.2.10 Refrigeration Recovery Unit

10.2.11 Expansion vessel Units

10.2.12 Chemical Treatment System

10.2.13 Exhaust / extract Fans

10.2.14 Generators

10.2.15 Compressed Air System



10.3 Electrical Works

10.3.1 Transformers

10.3.2 Switchgears

10.3.3 Starters

10.3.4 Earthing System

10.3.5 LV MCC Plant Works

10.3.6 NGR



10.4 Plant Automation Works (Including BMS - Plant & Building separate)

10.4.1 BMS Wiring

10.4.2 Hardware Installation

10.4.3 Software purchase

10.4.4 Development of Application

10.4.5 Integrate Software with System



10.5 Fire Protection Works

10.5.1 Fire Pump Systems

10.5.2 Fire Sprinkler System

10.5.3 generator deluge system

10.5.4 FM200 System

10.5.5 Fire Hydrant System

10.5.6 Fire Beam Detector System



10.6 Building services

10.6.1 CCTV Works

10.6.2 Normal Lighting Works

10.6.3 Emergency Lighting Works

10.6.4 Small Power Works

10.6.5 Lighting Protection Works

10.6.6 LV MCC Works

10.6.7 AHU’s / FCU’s

10.6.8 Battery Room / UPS



In Testing & Commissioning, include for all above items and add Power Connection with Main Supply (11/22kV)



The list is not complete and you may need to add components as per teh design of the DCP, but these are the key items which u need to incorporate in ur program.



In the project close-out u need to have items like System tune-up, submission of vendor manual, QA/QC Documentation, As-Built Drawings etc.



Feel free to ask if u need more details.



Regards,



Ravi

S
Shah. HB 👤 Member for 17 years 6 months

Hi Pacifico

I am posting the WBS concisely; you can break or merge for further level of detail to meet your project requirement



1.General [ NTP, Mobilisation, etc ]



2.Milestones



2.1 Contractual Milestones [Readiness of chillers for operation, Readiness of MV system to reactive power , etc ]



2.2 Project Milestone [ Power ON, Water & Drainage connection, etc ]



3.Information release/Design Availability

4.Free issue Items

5.Statutory Authority NOC’s

6.Provisional Sum

7.Engineering Details [Shop drawings, materials & method statements submission & approvals]

8.Procurement Management [ Order, mgf & Shipment ]

9.Civil Construction –Substructure, superstructure & External works

10. MEP Installations

11. Testing & Commissioning

12. Project Closeout

P
Pacifico Pallasigui 👤 Member for 22 years 4 months

Sirs,



Can anybody give the WBS of A District Cooling Plant we will be constructing the Riyadh complex and the cooling plant is included.



Thanks



Jun

S
Shah. HB 👤 Member for 17 years 6 months

Hi to all seniors



I am currently working in district cooling plant project as junior scheduler, and project is almost 70% over.



If i found any answer to your question i will post here

D
Dieter Wambach 👤 Member for 19 years 4 months

Hi Mike



So we both agree that we must have a profound understanding of the process. "Build" for my understanding is what my father and I did with my parents house.



Regards



Dieter

M
Mike Testro 👤 Member for 20 years 5 months

Hi Dieter.



I have - in my early career in building - laid bricks and pitched roofs but that is only a part of being a builder.



What is needed is a full understanding of the construction process and how the many elements interface and affect each other.



When you have that level of experience you can call yourself a builder and only then can you plan a project.



If you do not have that level of experience you can only schedule a programme to someone elses plan.



Added to this is my other maxim:



"Keep learning and if you don’t know ask someone who does."



I do react aversly to PP members who are completely out of their depth begging for sample programmes - I now realise that Ravi was not doing this but in his #1 thread it seemed like he was.



Best regards



Mike Testro

D
Dieter Wambach 👤 Member for 19 years 4 months

Dear Mike



"If you can’t build it you can’t plan it." In my humble opinion you devalue the profession "Planner". You must have a understanding of all parts of the project you’ll have to plan but there is no need to be a brick-layer and an electrician and a plumber and a carpenter and a welder and a process engineer and an advocat (legal issues of a project!) specialised in that country you’ll have to run that project, and ...

In contrary: It’s impossible to know each detail of a project. So, one essential capacity of a planner is: Communication skills - e.g. ask, if you don’t know a detail.

This is one advantage of PP.



"If you can’t build it you can’t plan it." in my opinion would prevent from learning. Each project is a challenge to learn something new, to expand knowledge. If a planner would tell me, "I can’t plan this project because there are details I never built", this would be a reason to separate from her/him. IMHO



Ravi

sorry for misusing your thread.



Regards



Dieter


A
A D 👤 Member for 19 years

Mike,



First of all let me tell you that it’s because of people like you and Dieter with such a huge experience make this (Planning) planet lively. Ur experience is more than our age. But, things go nasty sometimes, and u require that (lethal) cocktail.



Anyway, as said in my post # 01, I have the manufacturer’s list and i do have contact with some of the vendors but not all.So, I still require some experts advise so that i dont miss anything.



What I call that lethal sounding cocktail -----?? (We can call that as .............. "Charlie Orbe’s" cocktail)



Cheers,



Ravi

M
Mike Testro 👤 Member for 20 years 5 months

Hi Deiter



Thanks for calming this thread down.



Hi Ravi



I was not responding to your thread as a Moderator but as a PP member who is trying to spread a simple message.



If you can’t build it you can’t plan it.

You can schedule someone elses plan - so ask someone who does know how to build it.



It is best to ask someone in your own company who will then have to stand by the advice given to you.



Now that you have clarified your request and narrowed it down to risk and pinch points maybe there is someone in PP who can help you.



As in most industrial plants it will probably come down to the time required for testing and commissioning the various elements and then the whole plant.



Best regards



Mike Testro.



PS I worked in Baghdad when Saddham was in charge and it was one of the best postings ever.



PPS - What do you call that lethal sounding cocktail?

D
Dieter Wambach 👤 Member for 19 years 4 months

Ravi



I understood your first question in a similar way as Mike, I’m afraid. Thank you for clarification.



But I’m sorry, I never planned this kind of plant.



Regards



Dieter

A
A D 👤 Member for 19 years

Dieter,



My question was very simple. As far as civil and MEP works goes or commissioning of items like pumps & motors, i know to a certain extent. But if somebody has already carried out District Cooling Plants, they must be knowing some tricks of the trade for better planning and scheduling and making sure RISK remains less and there are no surprises.



That was my question and nothing beyond that.



As far as sharing of plans is concerned, i fully agree with u and we have to follow certain ethical codes as a professional and not share plans at least. Thats why i never asked for any plans but just sharing of any special info (Tricks of the Trade) which may help for successful completion of the project.



TEA? I think its time for some vodka, mixed with some coconut rum, cream of almond, sweet vermouth with a dash of limejuice.



:-)

D
Dieter Wambach 👤 Member for 19 years 4 months

Ravi



Please calm down! In my opinion of course you can put questions as in post #1. But please be aware that we are paid by employers to create plans for THEM. They own the plans. I’m sure that you won’t publish one of your plans in this forum or to another planner - if not a colleague. I won’t do it as well. Maybe you’ll ask a bit more specific - e.g. for special problems (lead-times, suppliers), technical issues ....



For specific questions, no doubt, you’ll receive appropriate answers.



Mike, in Germany British gentlemen are famous for their sense of humour and their politeness.



Is there a chance for a virtual tea? Indian or British?



Best regards from Germany



Dieter


A
A D 👤 Member for 19 years

U r going in a totally wrong direction.



This forum is for sharing our experience and NOT the way u think by just sharing some key information, my work will be over.



Now, if u ask me anything about pre-engineered buildings, fabrication works, infra works including pipeline works, definitely i can share some good information, which i have done from last couple of years on this forum.



What make u think that just by sharing some lesson learned from previous project, my work will be over. Is this how people work in european countries?? I Dont think so.



If u dont know anything about District Cooling Plant, then at least let others guy share their experince.



If u keep on posting things like this, and act more of a Saddam Hussain / Hitler on this forum, I will think twice to visit this site.



Guys like Arnold Puy and Dieter have shared a lot of info on this forum and they might have never ever thought of these things in their mind.



There are lot of speacilized projects on which its very difficult to get info online and especially if ur co. has entered into a new venture. I thought this forum is RUN BY PLANNERS FOR PLANNERS.

M
Mike Testro 👤 Member for 20 years 5 months

Hi Raviraj



You don’t want much do you - just for some PP members to do your job for you.



Take your time and do it yourself.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts