Copying a cost loaded project
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Gern geschehen! (Youre welcome)
Dieter
Danke schon Dieter!:~)
Cristina
Cristina
This is the right approach - we created an EPS-branch "Archive" with special access rights. Change the project status to "What-if".
In addition check the entry under Edit --> User Preferences --> Resource Analysis. Its self explaining and should be according to your needs.
Regards
Dieter
OK, I think I found a way. I created a new branch in the EPS structure for Project Copies, and will locate all my copies in there.
Cristina
Now the problem is...hmmm...the system adds up the data(activites & budget) from my original project + copies. Now I understand why the copies were showing a zero before summarizing.
Where should I locate the copies in order not to affect the EPS info?
Thankfully,
Cristina (obviously I am a beginner in P6)
It worked. Thank you guys. Now the data shows on all projects (original + copies).
Cristina
Cristina
Tools --> Summarize --> Open Projects (or All Projects if not open)
Regards
Dieter
Cristina
The only thing I can think of is to open and summarise the copied project then the info should show up in the projects view
Shimmo
Hi Cristina,
Sorry, its not so clear can you explain a little bit in detail.
Regards,