Negative Total Float Issue
Forum Sponsor
Top Posters
Saqib Ullah
1 posts
Luyanda Ndlumbini
2 posts
Jeff Waldrop
6 posts
Robert Roy
1 posts
Tony Wright
4 posts
Arshman
0 posts
Stan Remiszewski
1 posts
GeoVe
0 posts
JAGAN REDDY MUSUKU
0 posts
Nick Johnson-Pond
3 posts
Thnk u Mr Velmurugan Selvan. . .
I ws also hvng the same problem bt nw it solve. . . thank u sir. . . .
Hi Buddies,
My problem is related to the above maybe you can advice me also, the scenario is predecessors had 100% complete and successor something around 30~60% progress then followed by no progressed successors, the on progress activities has avery huge TF which is longer than project duration where as the not progressed successors only shows 2 months of TF.
Zeggie
THX
Hi Velmurugan
Did you notice that this thread is two years old?
It is not a good idea to respond to long dead threads.
Best regards
Mike Testro
Hi,
This will solve your problem "Negative Float in the critical path"
When you apply "Must Finish By" constrain to the project finish date, primavera will default to take the project end date and time as 12:00 AM regardless to date, that's the reason it shows the Negate float.
On ground the project end by the end of the day depending up on the project & type, let we assume the project will end by 4:00 PM.
Now enable time hour units in User preference and see the project end date and hours, e.g. 24 May 2011 4:00 PM, now set the must finish date to 24 May 2011 12:00 AM (which primavera assumes default) to 24 May 2011 4:00 PM, schedule the project.
Nowyou can see the critical path without negative float.
If the problem is not fixed by the above means, then the project links & scheduling options to be checked.
Cheer up.............
Shahul
Baseline Schedules should never show negative float in any case some positive float as use of buffers should be allowed; unfortunately use of buffers is not a widely accepted practice in my location, in occasions prohibited by some specs.
The only reasons I can think of at this moment for a schedule to show negative float are the effect of constraints (internal and/or external) or the effect of out-of-sequence progress.
Your statement - I guess use of negative float is not recommended by Consultant and delay analyst, but I have no idea about it. – is supported by some specifications that prohibit the use of negative float as a basis for EOT claims. With a Google search you can get plenty of samples.
Best regards,
Rafael
Mr.Rafael initially when baseline is prepared normally it wont have negative total float except introduction of must finish dates.then on scheduling total float becomes -ve due to actual dates and % of completion introduction? or is there any other reason for negative total float?
Mo He
I know you said that the activities have no progress whatsoever. But I would like to rule out the possibility this is caused by out-of-sequence events.
Check in the out-of-sequence report if any of these activities are listed as being out-of-sequence.
If any is listed as out-of-sequence this might be the cause as a common reason for negative float is out of sequence activities, sometimes referred to as broken logic. This often occurs if the schedule has been part progressed and actual dates have been added.
If you set an actual start date with 0%progress this is in CPM terms an activity with progress and this might still be able to cause an out-of-sequence event.
Also if you set a successor to these activities with an actual start, again even with 0%progress this might also cause these activities to be out of sequence.
First you got to rule out out-of-sequence then if occurs you got to find why.
Best regards,
Rafael
sorry i meant negative lag
I guess use of negative float is not recommended by Consultant and delay analyst ,but i have no idea about it
Velmon:
Please refer to my query entitled " Bearing negative float if applies must finish date" it was answered by Arnold.
Cecil
Dear All,
Im having the same problem.
I just establish a schedule, and im presently reviewing my logical links. I just observe that my critical activities are negative floats and equal to the total durations of the project. Normally the critical activities should be zero, if the must finish by is not set. Please help me on this, may be in initial set up it requires some options to do the calculation of float.
Hoping for immediate response.
Thanks,
Velmon
Did you import them from some where else and have the been assigned a External dates, which acts like a constraints.
Show the External date columns to check.
Paul E Harris
Eastwood Harris Pty Ltd, Melbourne, Australia
Planning and Scheduling Training Manual & Book Publishers, Consulting and Training
www.eh.com.au
www.primavera.com.au
Hi Mo He
In Addition to Mike & Dieter
Try to Filter Lay out
for Negative Float
And Look for the reason By Negative Float activities
And its Gant Chart
Hello Mo He
for better understanding can you pls give the dates for:
start, finish
Early dates
Planned Dates
Actual Dates
and Expected Finish
for all three activities
Regards,
Hannes
Hi Mo He,
In addition to their information, try to check your Project Detail --> Dates --> "Must Finish By".
Regards,
Arnold
Have you checked for external dates?
Also, p3e used to be a bugger for retaining ghost links to dead activities - although I only ever saw that on other peoples machines, if all else fails try deleting and reinstating the activities with spuriously low float.
Mo He
Just by your description and answers to Mikes and Garys questions I have no idea. Did you check these activities with the trace logic?
Please inform on Primaveras answer.
Regards
Dieter
Hi Mo He
The two negative float activities must be showing critical.
Filter on critical activities - or even super critical - and you may get a clearer view of the problem.
It is most likely a "must end on" constraint down stream of the problem activities.
Alternatively just take ALL contraints off and re-schedule.
Best regards
Mike Testro
The activities have no progress whatsoever. There are some constraints in the project but not in these activities. The project is not resource loaded. There may be progress in activities downstream but how it would affect those simple sequenced activities. I emailed the problem to Primavera and they are researching but didnt give me a clue yet. I have this issue in several locations in the project but this is the case that has no doubt.
Thanks,
Mo
Hi Mo He
If you are sure that there are NO constraint flags enywhere on your project then check:
1. Does your calendar extend beyond the work end?
2. Do any resources have different calendars?
3. Are there any link loops in the logic?
4. Have you put in any progress on down stream activities?
Otherwise you have a software glitch.
Best regards
Mike Testro.
Do any of the activities have actual start or finish dates, or percent complete > 0%, or remaining duration < original duration?
The three activities are linked to each other without constraints or relationships other than FS. The calendar is the 5 day calendar for all of them.
thanks,
Mo
Mo He
In addition to Mike. Did you check the calendars of those activities? Float is based on the activitys calendar - sometimes misleading.
Dieter
Hi Mo He
You do not explain the logic links between the three activities - are they FS with no lags?
There could be constraints further down the line.
Or maybe there are conflicting calendars or work patterns.
Filter & check the whole critical path to isoltae the problem.
Best regards
Mike Testro