Hi ,

How to calculate the resources in tentative stage and how to apply in P6. 

Please anybody help me with some example....

 

 

 

 

Thanks 

Siddic K

K
Khuong Do 👤 Member for 17 years

Hi.

That’s right, you have to key in Est weight for each activity base on your experience.

Then run Top down estimation in Tool menu.

K
Kumar J 👤 Member for 24 years 11 months

Dear Sir,



Whether i will have manually key in all est weight values against each activity?



If i need to enter manually, then, i will check for S Curve as suggested by you.



Regards,

K
Khuong Do 👤 Member for 17 years

You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.

K
Khuong Do 👤 Member for 17 years

You can choose S-curve to display base on early or late date by setting option in Edit -> User Preference -> Resource Analysis.

K
Khuong Do 👤 Member for 17 years

Hi Bharath

Est weight is used for Unit Top-down estimation. Let say you have 1000 unit, base on activity’s Est weight Primavera will deliver units to each activity.

K
Kumar J 👤 Member for 24 years 11 months

Can anyone guide the use of Est Weight in Primavera P6.



Regards,

Kumar

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts