Recovery Progress Curve

F
Ferdinand Fincalero, PMP 👤 Member for 17 years 10 months

Ajith,



Try checking out your calculation settings. Go to projects, calculation tab, then tick on "recalculate actual..." and "link actual..."



Hope it will do.

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Ajith,



You need to update your Actual & Earned Value Cost based on the % complete or work done.



Likewise, make sure that in Project Setting under Calculation, mark the check box next to "Subtract Actual from At Completion".



Regards,



Arnold