Recovery Progress Curve
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Ajith,
Try checking out your calculation settings. Go to projects, calculation tab, then tick on "recalculate actual..." and "link actual..."
Hope it will do.
Hi Ajith,
You need to update your Actual & Earned Value Cost based on the % complete or work done.
Likewise, make sure that in Project Setting under Calculation, mark the check box next to "Subtract Actual from At Completion".
Regards,
Arnold