Claim

J
James Young 👤 Member for 17 years 11 months
A
A D 👤 Member for 19 years

You may please go through book by Roger Gibson on "Extension of Time and Prolongation Cost".



Its cheap compared to other books on contract.


S
Samer Zawaydeh 👤 Member for 17 years 10 months

Dear James,



You can start with following these basic requirements that were handed over to me during on seminar:



1. Must be Based on Contract Clauses.

2. Timely Notice Required.

3. Proof of Entitlement

4. Proog of Damages

5. Cause and Effect Relationship Required

6. Burden of Proof

7. Mitigation Requirements.



Follow these steps for each event that you have. Compile the supporting documents and then you start considering them in your As Built Program.



We will make sure that you get the best advice. The more you ask the better information you have.



With kind regards,



Samer

M
Mike Testro 👤 Member for 20 years 5 months

Hi James



Not heard from you for a while.



Samer’s advice is correct for the contractual veiwpoint but you need some more nitty gritty advice.



An As Built Programme is only the Start.



To set this up start with a Spreadsheet - I know you only have excell but Lotus 123 will do it much more elegantly (£86.00 worth the investment for the download)



Set Down in columns.



Doc Ref - Where the data is from

Description - what work is described

Activity - Cross reference to the programme activity.



From this starting point you can establish the days when work on any activity is being done.



This data can be transferred to the barchart to compare the As Planned v The As Built (don’t ask me how - I have been doing this for years and i am not about to pass the secret on)



Now the real task begins:



Set up a detailed Events Schedule on a spreadsheet -

Set down a number of column headings:



Date

Doc ref

Sent From

Sent To

Desription What is said in the document

Start Date When the event started - not the same as the Doc date - an AI could be retrospective.

Lead Time How long before the changed work can be started

Task Imopacted A description of the activity likely to be delayed.



Now you have the starting point for a delay analysis which - following Samer’s points may lead you to a succesful outcome.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts