Constraint at Completion Date

E
Edniel Recamadas 👤 Member for 17 years 1 month

Dear Dieter,



Thanks, excellent advise for having the constraint at activities level.



Regards,

Edniel

D
Dieter Wambach 👤 Member for 19 years 5 months

Dear Edniel



In my opinion it’s better to use a milestone "Project Finish" with a mandatory finish date. Why? If you control your program you’ll have a look at the Gantt chart or the network within the view "Activities" - not at the view "Projects". The "must finish by" entry will be hidden.



The effect for the calculation of your schedule will be the same.



Regards



Dieter

F
Ferdinand Fincalero, PMP 👤 Member for 17 years 10 months

Dear Edniel,



"Must finish by" is a contractual target so I see nothing wrong in constraining the program with a particular project completion date. It is a good way for it will aid your scheduling and schedule update process to determine whether you are going beyond the contractual completion period by way of having negative float in the overall summary bar.



Hope this helps.



In Friendship & Service,

Ferdinand

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts