Description The Duration Variance field contains the difference between the baseline duration of a task and the total duration (current estimate) of a task.
How Calculated The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. Microsoft Office Project 2003 then calculates duration variance as follows:
Duration Variance = Duration - Baseline Duration
Best Uses Add the Duration Variance field to a task sheet when you want to analyze whether your schedule is taking more or less time than originally planned.
Example You set a baseline for your project three months ago, and you now want to review duration variances for the tasks. You add the Duration Variance field to the Task Sheet view to analyze the projects progress and performance to date.
Remarks If the duration variance is a negative number, the task is scheduled to take less time than originally planned. If the duration variance is a positive number, the task is scheduled to take more time than planned. If the duration variance is zero, the task is taking exactly as much time as originally planned.
The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. To set a baseline, point to Tracking on the Tools menu, and then click Save Baseline. This copies the current value for the scheduled Duration field into the corresponding Baseline Duration field.
You can use the Tracking Gantt view to see the duration variance shown graphically with Gantt bars.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
faisal
duration varialnce is the difference between the planned & actual duration...
Duration Variance (task field)
Data Type Duration
Entry Type Calculated
Description The Duration Variance field contains the difference between the baseline duration of a task and the total duration (current estimate) of a task.
How Calculated The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. Microsoft Office Project 2003 then calculates duration variance as follows:
Duration Variance = Duration - Baseline Duration
Best Uses Add the Duration Variance field to a task sheet when you want to analyze whether your schedule is taking more or less time than originally planned.
Example You set a baseline for your project three months ago, and you now want to review duration variances for the tasks. You add the Duration Variance field to the Task Sheet view to analyze the projects progress and performance to date.
Remarks If the duration variance is a negative number, the task is scheduled to take less time than originally planned. If the duration variance is a positive number, the task is scheduled to take more time than planned. If the duration variance is zero, the task is taking exactly as much time as originally planned.
The Duration Variance field contains "0 days" until the duration value varies from the baseline duration value, as shown in the Baseline Duration field. To set a baseline, point to Tracking on the Tools menu, and then click Save Baseline. This copies the current value for the scheduled Duration field into the corresponding Baseline Duration field.
You can use the Tracking Gantt view to see the duration variance shown graphically with Gantt bars.
Hello,
just display the Variance table in the Task sheet
Alexandre