Is this what you are looking for?
Best regards,
Rafael
Hi Jonathan,
If you dont mind, can you send me the screenshot of what your delimma is, and showing what you want to happen (before & after). My email address is [email protected]
I will send you the steps if it is possible.
Regards,
Arnold
Jonathan
I use SureTrak and do not have P6 but I explored the software for 2 weeks. I still have a copy of the manual the license owner gave me to help him. What you are asking I can easily do with SureTrak and with PowerProject seems like a walk in the park with some additional goodies as a jagged progress line.
It occurs to me you can do it with the Baseline as a separate project.
1.Detach your Original Baseline.
2.Create a Copy of your Original Baseline. Set New Baseline Copy update setting to manual, not auto.
3.Reattach your Original Baseline.
4.Update percent completes on your New Baseline Copy but do not reschedule. Never reschedule, just update percent complete or remaining duration.
5.Manually draw your New DD line; a red vertical line should do it.
Can you see what you wanted? Try updating just a couple of activities before going on with the remaining.
Best regards,
Rafael