I corrected myself in my post no. 2. Actual start should be 29-Sep-08.
I thank you for sharing your idea. I think that is the fundamental in P6. Now I understand.
Dear Johnny,
I appreciate your sharing of ideas. Now I will use only start and finish column in P6 so that I will not be confuse since my mind is still thinking like P3.
I thank you all for helping me. More power to you all.
Early Start is the earliest possible date the remaining work for the activity can begin, once the activity has started, the Remaining Start is equal to the Data Date. Try to display the Early Dates in your column.
I am wondering your start date is 29-Sep-08 and your actual start date is 29-Sep-09, is this correct? If I understood you the baseline start date is 29-Sep-08, am I right? It means that you are 1 year behind of the target start date? Correct me if I am wrong.
Late Start is 30-Sep-08 and Early Start is 26-Jun-09, if you are going to subtract these two dates considering 7 days a week calendar, you will get 270 days float.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Dear Arnold,
I corrected myself in my post no. 2. Actual start should be 29-Sep-08.
I thank you for sharing your idea. I think that is the fundamental in P6. Now I understand.
Dear Johnny,
I appreciate your sharing of ideas. Now I will use only start and finish column in P6 so that I will not be confuse since my mind is still thinking like P3.
I thank you all for helping me. More power to you all.
Many thanks,
Scarlett
in p6
ES is not like p3.
ES will be equal to activitys remaining start or equal to DD once it already progressed.
use the START date in P6 not ES.
LF minus EF equals TF = 324
Hi Scarllet,
Early Start is the earliest possible date the remaining work for the activity can begin, once the activity has started, the Remaining Start is equal to the Data Date. Try to display the Early Dates in your column.
I am wondering your start date is 29-Sep-08 and your actual start date is 29-Sep-09, is this correct? If I understood you the baseline start date is 29-Sep-08, am I right? It means that you are 1 year behind of the target start date? Correct me if I am wrong.
Late Start is 30-Sep-08 and Early Start is 26-Jun-09, if you are going to subtract these two dates considering 7 days a week calendar, you will get 270 days float.
Can you please check again your data?
Regards,
Arnold
actual start should be: 29-Sep-08
I apologize for the inconvenience.
Many thanks,
Scarlett