Rafael Davila 👤 Member for 22 years 3 months

Shahzad



Construction activities are performed by crews, their composition is to be balanced with the tools and equipment. Allowing the software to change the units/time, which is the composition of your crew, is not a good idea.



Although I use Primavera SureTrak, the P6 equivalent of my preferences should be:



For resources whose total amount is to be determined by duration and units/time select Fixed Duration & Units/Time. These are usually labor (personnel) and Nonlabor (equipment) resources. For resources whose total amount is fixed while units/time is not, select Fixed Duration & Units. These are usually materials resources. The activity’s duration does not change regardless of the number of resources assigned when you modify or update activities. You usually choose these duration types when you are using Task Dependent Activities.



Avoid using percent complete to determine your remaining duration and do not select any option that allows the software to manipulate activity duration.



Best regards,

Rafael


Forum Sponsor

Top Posters

Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts