Thank you Rafael. This was well stated. I fully agree with your assessment of out-of-sequence logic and the argument of retained logic v progress override.
I am working with a client who would like to stipulate in their contract that specific calculation rules be used when submitting schedules. They are specifying retained logic, Durations contiguous (not interruptible) and Float calculated on Finish Dates.
I am having difficulty providing documentation on these calculation methods.
Under P3/SureTrak if an activity has been worked on (had progress) before one of its predecessors, choose how to display this out-of-sequence progress. When you choose Retained Logic, P3/SureTrak does not schedule the remaining duration of a progressed activity until all of its predecessors are complete. When you choose Progress Override, P3 ignores network logic and allows the activity to progress without delay. Neither option solves the issue of out-of-sequence; there are arguments in favor and against each method.
Because you are looking for the option under MS Project I assume you know that.
I believe you can set this under Tools/ Options/ Schedule, split in progress check box.
Split in-progress tasks Allows rescheduling of remaining duration and work when a task slips or reports progress ahead of schedule. With this check box selected, if progress is reported on a successor task before the predecessor task is completed, the remaining work on the successor task can be shown as a split, using the same task dependency with the predecessor on remaining work. If this check box is cleared, remaining work is not split. The progress information is recorded on the originally scheduled dates, regardless of when the actuals took place. Likewise, remaining work is not rescheduled to maintain the task relationship. By default, this check box is selected.
A matter of semantics.
The major problem I had with MS Project with this regard is the lack of a report that identifies the existence of out-of-sequence and where. I tried to get a VB script to this purposes and never got it. For your knowledge there are some add-on packages that provide these reports but at extra cost.
These reports are usually a listing of your out-of-sequence activities (tasks in MS Project language) their predecessors and type of relationship. These reports are essential as out-of-sequence might invalidate your update unless you solve the issue through changed logic. Out-of-sequence at times drives crazy some reviewers who do not understand the issue. Out-of-logic is common, is not a sin, and per-se alone does not mean bad planning but a change in course.
Sorry, I think Retained Logic is mostly used with the Primavera toolset and maybe one or two others. There isnt a suitable equivalent in MS Project as it doesnt use remaining duration to calculate EF or LF dates, only start dates and durations (and float of course).
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Handling out-of-sequence
Retained Logic vs. Progress Override
Retained logic and Contiguous Durations are mutually exclusive per software settings, unless you make the exception for in-progress tasks.
It is your choice.
Best Regards,
Rafael
Thank you Rafael. This was well stated. I fully agree with your assessment of out-of-sequence logic and the argument of retained logic v progress override.
I am working with a client who would like to stipulate in their contract that specific calculation rules be used when submitting schedules. They are specifying retained logic, Durations contiguous (not interruptible) and Float calculated on Finish Dates.
I am having difficulty providing documentation on these calculation methods.
Any thoughts?
Regards,
Donna
Donna
Under P3/SureTrak if an activity has been worked on (had progress) before one of its predecessors, choose how to display this out-of-sequence progress. When you choose Retained Logic, P3/SureTrak does not schedule the remaining duration of a progressed activity until all of its predecessors are complete. When you choose Progress Override, P3 ignores network logic and allows the activity to progress without delay. Neither option solves the issue of out-of-sequence; there are arguments in favor and against each method.
Because you are looking for the option under MS Project I assume you know that.
I believe you can set this under Tools/ Options/ Schedule, split in progress check box.
Split in-progress tasks Allows rescheduling of remaining duration and work when a task slips or reports progress ahead of schedule. With this check box selected, if progress is reported on a successor task before the predecessor task is completed, the remaining work on the successor task can be shown as a split, using the same task dependency with the predecessor on remaining work. If this check box is cleared, remaining work is not split. The progress information is recorded on the originally scheduled dates, regardless of when the actuals took place. Likewise, remaining work is not rescheduled to maintain the task relationship. By default, this check box is selected.
A matter of semantics.
The major problem I had with MS Project with this regard is the lack of a report that identifies the existence of out-of-sequence and where. I tried to get a VB script to this purposes and never got it. For your knowledge there are some add-on packages that provide these reports but at extra cost.
These reports are usually a listing of your out-of-sequence activities (tasks in MS Project language) their predecessors and type of relationship. These reports are essential as out-of-sequence might invalidate your update unless you solve the issue through changed logic. Out-of-sequence at times drives crazy some reviewers who do not understand the issue. Out-of-logic is common, is not a sin, and per-se alone does not mean bad planning but a change in course.
Best regards,
Rafael
Does anyone know where I can find documentation on the calculation method used by microsoft?
Hi Donna,
Sorry, I think Retained Logic is mostly used with the Primavera toolset and maybe one or two others. There isnt a suitable equivalent in MS Project as it doesnt use remaining duration to calculate EF or LF dates, only start dates and durations (and float of course).
Can anybody else help?
Regards
Darren