Perhaps Im labouring under a misapprehension, I thought the impenetrable predicament Faisal has found himself in was more to do with erroneous duration variance, as opposed to seeking advice on constructing a schedule based on sound precedence networks.
If such is the case Ill extricate myself from this thread, as its a theoretical lesson he needs not hands-on issue resolution.
All valid points, however, to specifically calculate duration variance MS Project doesnt need to use closed network or critical path as a reference, just a baseline. Now heres one to get your wind up ;o)
Are ALL of the task durations whole days and not decimals?
Are ALL of the baseline task durations whole days and not decimals?
Are ALL of the tasks using the same task calendar?
Are ALL of the resource base calendars the same as the task calendar?
Do the default options on the calendar tab match the task and resource base calendars?
If you change the date format to show ddd dd/mm/yy hh:mm, are ALL of the start/finish times the same as the default options on the calendar tab?
And finally, are ALL of the baseline start/finish times the same as the default options on the calendar tab?
You calculate the Duration Variance from Duration - Baseline Duration, so you need to check all possible associations between the two.
How do you know that there are no date constraints?
Can you see the Indicators column?
Is there a "calendar" icon in it?
Do you have a complete, closed network, with every Task having at least one FS predecessor and at least one FS successor?
If you have a complete, valid CPM network, then if your tasks that have started started late, or took longer than estimated, or finished later than their early finish, and if they are on the critical path, then when you update them the project finish date will move right. Not happening?
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Hi Darren
We now find ourselves debating Faisals problem when he hasnt a clue what to do about it even after all the advice.
I will now follow you to the nearest exit route on this thread.
Best regards
Mike Testro.
Mike,
Perhaps Im labouring under a misapprehension, I thought the impenetrable predicament Faisal has found himself in was more to do with erroneous duration variance, as opposed to seeking advice on constructing a schedule based on sound precedence networks.
If such is the case Ill extricate myself from this thread, as its a theoretical lesson he needs not hands-on issue resolution.
Regards,
Darren
Hi Darren
The situation friend faisal is facing is when a 20 day delay at the begining of the job generates a .25 delay at the end.
No one has yet advised him od what to do to get the programme moving dynamically.
Best regards
Mike Testro
Mike
All valid points, however, to specifically calculate duration variance MS Project doesnt need to use closed network or critical path as a reference, just a baseline. Now heres one to get your wind up ;o)
Faisal
Are you using leads or lags?
Hi Faisal
Please go back to my thread #4.
Are you using up excessive float?
Do you have a clear critical path?
Are all the links in place?
Best regards
Mike Testro
okie plz suggets me a solution
For a start Id download Service Pack 2 just to be sure and then see if the problem persists.
nope for both
Do you split in-progress tasks?
Have you download SP2 for MS Project 2k7?
no i am not using elapsed duration
Faisal,
Are you using elapsed durations? (e-days)
Is your calculation mode set to manual or automatic?
Regards,
Darren
yes to all your queries darren
Hi Faisal,
Are ALL of the task durations whole days and not decimals?
Are ALL of the baseline task durations whole days and not decimals?
Are ALL of the tasks using the same task calendar?
Are ALL of the resource base calendars the same as the task calendar?
Do the default options on the calendar tab match the task and resource base calendars?
If you change the date format to show ddd dd/mm/yy hh:mm, are ALL of the start/finish times the same as the default options on the calendar tab?
And finally, are ALL of the baseline start/finish times the same as the default options on the calendar tab?
You calculate the Duration Variance from Duration - Baseline Duration, so you need to check all possible associations between the two.
Regards,
Darren
i can see the indicators column any help plzz fast
Faisal,
How do you know that there are no date constraints?
Can you see the Indicators column?
Is there a "calendar" icon in it?
Do you have a complete, closed network, with every Task having at least one FS predecessor and at least one FS successor?
If you have a complete, valid CPM network, then if your tasks that have started started late, or took longer than estimated, or finished later than their early finish, and if they are on the critical path, then when you update them the project finish date will move right. Not happening?
Hi Faisal
Are you using up float?
Best regards
Mike Testro
there are no constraints in the project
Hi Faisal
It seems as if you have some constraint flags that are distorting the critical path.
Remove them all and re-schedule.
Best regards
Mike Testro