Urgent -Factory building

V
Vrinda M 👤 Member for 18 years
S
Samer Zawaydeh 👤 Member for 17 years 11 months

Dear Vrinda,



I am not sure where the tower fits in the Factory, but the sequence of activities for the Factory would be as follows:



1. Site Layout.

2. Mechanical Excavation.

3. Manual Excavation up to Bottom of Foundation.

4. Blinding formwork

5. Casting of Blinding.

6. Shuttering of Foundation.

7. Reinforcement of Foundation.

8. Casting of Foundation.

9. Shuttering of Foundation necks up to bottom of tie beams

10. Reinforcement of Foundation necks up to bottom of tie beams.

11. Concreting of Foundation necks

12. Insulation of Foundation.

13. Fill in layers up to bottom of tie beams

14. Shuttering of Tie beams.

15. Reinforcement of Tie beams.

16. Casting of Tie beams

17. Insulation of Tie beams.

18. Fill in layers up to bottom of Tench and pit holes for machines.

19. Blinding for tench and pit holes.

20. Shuttering of foundation of trench and pit holes

21. Reinforcement of foundation of trench and pit holes

22. Install mechanical piping, if any.

23. Install embedded galvanized angles around tenches to receive trench covers later.

24. Casting of foundation of trench and pit holes

25. Fill in layers up to bottom of Slab on Grade.

26. Complete mechanical piping.

27. Repair layers of fill.

28. Blinding for Slab on Grade.

29. Insulation below Slab on Grade.

30. Protection of insulation below slab on grade.

31. Reinforcement of Slab on Grade.

32. Casting of Slab on Grade.



Hoping that the list is useful. If you have any specific requirement, please let us know.



With kind regards,



Samer




M
Mike Testro 👤 Member for 20 years 6 months

Hi Vrinda



You have the detailed drawings so you can work out a logical sequence for the foundations and the machine bases.



Just watch out for any vibration / noise isolators.



Put a milestone on the end of each base and see if it meets your clients deadline - if it doesn’t then tell him before you start.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Aidar Kurmantayev
0 posts
Noe Radovan
8 posts
GeoVe
0 posts
James Williams
74 posts
Johannes Vandenberg
14 posts
Soheil Barekat
4 posts
Peter Holroyd
51 posts
Neil Atkinson
5 posts
Trian Asmoro
1 posts
Erkan Polater
9 posts