Number of Days Delayed

A
Albert Balogo 👤 Member for 18 years

Hi HTH,



The target or baseline has been asigned, All I need to know is the number of days elapsed between the early finish of baseline and early finish of the current program (Time Varience). Actually, it can be determined through bar chart but it is impractical to check it one by one. Is it possible in P3 to reflect it on the columns list? Any options?





Thanks,



Albert