Number of Days Delayed
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
HI
i guess yes, see variance target 1, early finish
mimoune
btw, HTH: hope this help.
Hi HTH,
The target or baseline has been asigned, All I need to know is the number of days elapsed between the early finish of baseline and early finish of the current program (Time Varience). Actually, it can be determined through bar chart but it is impractical to check it one by one. Is it possible in P3 to reflect it on the columns list? Any options?
Thanks,
Albert
you need to assign a target to do that;)
HTH