Difficulties with OD, D% Complete & Planned Dates

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Sean,



1. Try to use physical % complete and not duration % complete. Even though your At completion duration is change the physical % complete will never change.



2. In order to make Start & Finish dates and Planned dates equal go to Admin Preferences --> Earned Value Tab, under earned Value Calculation, choose the "Budgeted values with planned dates".



Regards,



Arnold