Hi Shahzad,



You are welcome. It is okey for me as long as I am not busy.



Regards,



Arnold

S
Shahzad Ahmad 👤 Member for 18 years 4 months

Thanks so much for your time and reply.



in my project weight factor based on cost but i did not assign cost to the P6 Schedule.



may be i will distrub you again in case my project xcl.progress measurement sheet and P6 progress give me a different result.



as you advise me.



I will be update schedule based on phy.progress % obtaining through xcl.progress measurement sheet.



Thanks to all Planner without you difficult to work with P6



Thanks & best Regards

shahzad

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Shahzad,



If you are calculating weighted based on cost or units, for me I used to assign the weighted for each activity using Excel sheet and export it back to P6. This is easier than assigning them in P6.



At least you know these activities were already assigned using weight factor and there is no need for you to calculate them in P6 just simply update.



In addition, try also utilizing "Steps" and assign each activity according to their weight factor and update them by means of the Physical % complete and you will get better result.



Regards,



Arnold

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts