You can create new base methodologies in Methodology Manager by exporting an existing project in P3e and then importing it into MM. When you import the project you are given a choice on whether to use Actuals or Planned values for the existing project.
This is actually quite neat because you have a chance to improve your methodologies after they have been used - continuous improvement.
Jim
Project Architect is used to Import a Methodology from Methodology Manager into Project Manager.
You can either create a project through PA or import a Methodology into an exicting project.