Variance BL Finish NE 0
I have 400 activities in the programme.
How can i set filter in a report wizard to show the changes?
I wud suggest u to go for a filter with:
a) Longest PATH EQ YES
b) Early Dates WR ....... .......
If its a 40000 activity program & there is a major delay, then most of the activities finish date will definitely change.
Above two filters will give u the best result. Add BL start & finish AND varinace column.
If u want to create report, then u can go to TOOLS --> Reports --> Reports. U can have use standard reports or u can modify them as per your needs.
BTW, how many activities r there in ur program?
Cheers,
HI Raviraj,
Thanks for your reply. WHat exactly i want to do is:
I have a programme and we have a bi-weekly review meeting. I want to create a report which shows the activities which finish dates are changed from previous week. I can add column and compare, but i want to create a report, so i can run and present in a meeting.
Cheers!!
Kinnar
Hi Patel,
Do u want to comapre date by Date? Then add two more columns of BL1 Start & BL1 Finish. This will give you difference between target & current update dates.
You may also add VARIANCE COLUMN to compare the difference in days.
If u want to compare two different programs, then you may please use CLAIM Digger to compare required parameters.
Cheers,
not sure what you want, i supposed columns will do (dont need to filter)