how to do multi-level schedule?

N
niles luo 👤 Member for 20 years 6 months
M
Mike Testro 👤 Member for 20 years 6 months

Hi Niles



I have never used a WBS in any programme - it is a waste of time.



I just ignore it and let the software sort it out if it wants to.



Best regards



Mike Testro

N
niles luo 👤 Member for 20 years 6 months

Hi Mike,

Thank you very much for your help.

I have learned much knowledge from your detail information. But, WBS are not included in your reply. I wonder if you can give me some further information about WBS in multi-level scheduel.

Thank you,

Regards

Niles

M
Mike Testro 👤 Member for 20 years 6 months

Hi Niles



Level 4 is where the construction tasks are plotted and linked.



Each task shoud represent 1 trade in 1 location that is the right size for 1 trade to work on its own.



When you have put together all the level 4 tasks in each location then Level 3 is the summary bar that covers all the level 4 tasks.



When you have a number of level 3 summaries you set up a level 2 summary.



All the level 2 summaries then come under level 1 which is the project duration.



A simple example:



Level 4 = all tasks to build a house.

Level 3 = the summary bar for each house.

Level 2 = the summary bar for all the houses in the street.

Level 1 = the summary bar for all the streets in the development.



I hope that is clear.



Best regards



Mike Testro

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts