autocost for expenses in p5

F
faik ulku 👤 Member for 17 years 2 months
D
David Kelly 👤 Member for 21 years 8 months

Does it help to know that expenses are "autocosted" according to the activity’s "planned" dates, not their "early" dates"

M
Mark Porter 👤 Member for 18 years 10 months

Hi Faik,



A couple of other quick things that you could possible consider are:



1) You have the "Apply Actuals" privlege set as part of your project security profile,



2) The project is checked in & active,



3) You have resources assigned (that also have the auto-compute actuals checked) to the activities that you are planning on updating via the "Apply Actuals" function in the tools menu (I don’t think it works otherwise), alternatively, another option is to use the view => progress spotlight and then tools => Update Progress... to progress your activities. I haven’t actually done this so I will be very interested in your results

F
faik ulku 👤 Member for 17 years 2 months

Hi Mark



thank you very much, as i remember i attemted also apply actuals menu but nothing changed. i ll try it again.



regards

M
Mark Porter 👤 Member for 18 years 10 months

Hi Faik,



If the auto compute acutals option is selected in the check box, the actual/remaining cost are automatically updated when project actuals are applied via the => ’Tools’ => ’Apply Actuals’ menu. This assumes that the expenses have been accured according to plan.



Note; If you also have any resources with the auto compute actuals check box selected, they will also be updated according to plan.



Without actually doing it myself, If I were aiming to update the expense % complete, my personal recommendation would be to export the activity data’s activity % complete to an excel spreadsheet, and then also export the expenses to excel and then I would perform a "lookup" function to apply the activity % complete to the expense % complete.



Hope that this helps



Kind Regards



Mark Porter

F
faik ulku 👤 Member for 17 years 2 months

i already did it but it doesnt work. strange. may be it is impossible for expenses

K
Khuong Do 👤 Member for 17 years

Hi.

You might need to choose the "Accrual type" of Expense to "Uniform over Activity".

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts