CLIENT REVIEW
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Shiv,
Try to check the following link:
http://www.aacei.org/technical/rp.shtml
http://www.aacei.org/technical/rp.shtml#53R-06
You can find out a lot of Analysis related to Planning & Scheduling.
HTH.
Regards,
Arnold
Shiv,
You should definitely do a float (trend) analysis. How quickly the float is being used up is a good indicator of how much risk their is to project or sectional completions. It is doubtful a contractor will volunteer this information.
Other things to look at:
-Critical Path analyis
-Lookahead schedule for upcoming client approvals & other non-contractor activities
-Productivity rates achieved vs. assumed for remaining works
-Exposure to potential EOT claims
-Does reported progress match reality on site, match payment claim?
Cheers,
G