Material allocation

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Rohit,



Go to Resources --> Units & Prices tab, under the Price / Unit Settings, input the any number you want to.



Regards,



Arnold

A
Arnold Puy 👤 Member for 19 years 1 month

Hi Rohit,



Create first the resource in the resources workspace after creating, change the resource type into material, so that you can assign the unit of measure. Then assign it to your activities.



Regards,



Arnold