ressource table

R
Rafael Davila 👤 Member for 22 years 3 months

Barry,



I found no way of doing this with Global Changes or Custom Resource Fields. Unless someone provides you with a somewhat automated procedure I believe you will end up doing it manually.



If you got to use a manual procedure then let it be orderly and in a way you can go back to your original resources definitions. To this purpose I would suggest the following approach.



For each resource you got to split, define a similar named resource with the prefix p for permanent and another resource definition with the prefix c for contract resources.



You will have to substitute the resource for each case you are using these resources until no resource is used under your original single definition for both, only then you can delete the old resource definition.



I found the use of prefix useful when in need to create resource groups for my Resource Profile/Table views.



Remember always to backup your job before any major changes are performed.



Good luck,

Rafael

R
Rafael Davila 👤 Member for 22 years 3 months

Click View

Click Resource Table

Click Display on Dialog Box

then Select the following options;

Display Type = units

Time Interval = Months

Table Calculate = Total

and select other options as needed.

Forum Sponsor

Top Posters

Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts