Usage of Percent Complete Types

D
Duy Huynh 👤 Member for 18 years 1 month
M
Marc Borburgh 👤 Member for 22 years 1 month

Physical:

Used with tasks were RD and PCT are not linked. Example: Engineering drawings have progress steps (10, 30, 50, 80, 100) that don’t relate to remaining duration, so you can set both separate.



Duration:

Your RD & PCT are linked, so basically your progress is linear with your duration.



Unit:

PCT is calculated based on your resource units. All planned units are summed (of all the resources on your tasks) and you will enter actual units for each resource. Based on this your PCT will be calculated.



HTH