I mostly use weighted detail spread sheet to substantiate where I obtain my % Complete from or in other words as a back up. This determines my % complete accurately and therefore use MSP as a time line exercise and the weighted spreadsheet as a mean to determine accurate % Complete for my activities and this is used for all disciplines when needed even up to and including commissioning.
I was only trying to help one of the members on the question on using % Complete to update - Yes use it that is what it is there for.
as Trevor said, "%Complete" refers to Duration, not Work or Physical; it is possible to update a task with %Work Complete or %Physical Complete:
a)display the Tracking Table (View, Table:(current table), Tracking,
b)then key in the correct figures
Be aware that MSP will compute the %Complete from the %Work Complete if the correct option is checked in the Options, Calculate dialog box; if the option is not checked, you will be able to enter both %Complete and %Work Complete independently (MSP2K7 SP0 has a bug at that stage)
MSP is unable to compute anything from the %Physical Complete, that is only used to display bars on the Gantt Chart.
You dont have to prove it can be done because of course you can use % Complete but I advise against it because it usually done wrong, and also it is unnecessary.
% Complete is not the same thing at all as how much of the task is done but that is often how it is used.
Since the planner must know the actual duration and the remaining duration, why not just use those and let MSP do the % Complete calculation?
If you have a 10 day task planned to start on Monday, and it actually starts on Tuesday and you inspect it on the following monday, and lets suppose 80% of the task is done (8000 bricks laid out of 10000), many people are tempted to type in 80% in the % Complete field.
If this is done, MSP will calculate the actual duration as 8 days. This is impossible since the task has only been underway for 5 days.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Trevor and all,
I mostly use weighted detail spread sheet to substantiate where I obtain my % Complete from or in other words as a back up. This determines my % complete accurately and therefore use MSP as a time line exercise and the weighted spreadsheet as a mean to determine accurate % Complete for my activities and this is used for all disciplines when needed even up to and including commissioning.
I was only trying to help one of the members on the question on using % Complete to update - Yes use it that is what it is there for.
hello all,
as Trevor said, "%Complete" refers to Duration, not Work or Physical; it is possible to update a task with %Work Complete or %Physical Complete:
a)display the Tracking Table (View, Table:(current table), Tracking,
b)then key in the correct figures
Be aware that MSP will compute the %Complete from the %Work Complete if the correct option is checked in the Options, Calculate dialog box; if the option is not checked, you will be able to enter both %Complete and %Work Complete independently (MSP2K7 SP0 has a bug at that stage)
MSP is unable to compute anything from the %Physical Complete, that is only used to display bars on the Gantt Chart.
Alexandre
It is a copy, paste to proove that you can use % Complete - so delete it
Hi Joel
This looks like it may be copyright material available to license holders.
Prove to me that it is not copyright before I delete the thread.
Best regards
Mike Testro
Joel,
I read your post before Mike pulled it off.
You dont have to prove it can be done because of course you can use % Complete but I advise against it because it usually done wrong, and also it is unnecessary.
% Complete is not the same thing at all as how much of the task is done but that is often how it is used.
Since the planner must know the actual duration and the remaining duration, why not just use those and let MSP do the % Complete calculation?
If you have a 10 day task planned to start on Monday, and it actually starts on Tuesday and you inspect it on the following monday, and lets suppose 80% of the task is done (8000 bricks laid out of 10000), many people are tempted to type in 80% in the % Complete field.
If this is done, MSP will calculate the actual duration as 8 days. This is impossible since the task has only been underway for 5 days.
Hi Joel
Thanks for your prompt reply.
There is no problem in setting down a website address that can be accessed by password holders - but not the whole copy.
Your thread has been deleted.
Best regards
Mike Testro
streetboy,
1. select the task,
2. go to Tools, Tracking, Update Tasks (not Update Project)
3. enter actual start daten, % complete OR actual duration (MSP will compute one from the other), possibly a new remaining duration if you know it
4. if you reschedule the project (Update project, last option) afterwards,
a) the schedule date is before the "complete thru date" of the task: MSP does not do anything
b) the schedule date is after the "complete thru date" of the task: MSP will split the task
Hope this helps,
Alexandre
But i Wanna enete % Complete an i do not know the actaul remain duration
Steps 1,2,3 are wrong.
Set Status Date (Project, Project Information)
Use Tracking Gantt View, Tracking Table, Tracking Toolbar.
Input Actual Start date
Input Actual Finish Date if the task is finished.
If not, input Actual Duration.
Then check Remaining Duration and revise up or down if necessary.
Do not enter % Complete, MSP calculates that for you.