Float Float Float How many are there......?
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
I think you are right that this part of the definition is just a mistake due to sloppy language, since "Brought Forward" appears to mean earlier but float is only about how much delay, ie later.
Not sure about the definitions for float in the “Planning Engineers Organistaion – Glossary of Terms”.
As float is calculated using the early dates, I don’t understand how the activity can be ‘brought forward’. Can anyone explain the basis for the ‘brought forward’ part of the explanation.
In relation to Free Float – I believe it is how long the activity in question can be delayed before it affects the start of the earliest successor activity.
The definition as I understand it is ES earliest successor – (ES+duration) of activity being calculated.
Greg
just following
cheers
Kunle
Chris,
"Free Float"
"The period by which an activity, or group of activities, can be delayed, brought forward or extended without affecting any other tasks, or the Programme End Date."
Im not sure with this one, but for me, "free float" is the amount of time an activity or group of activities can be delayed, brought forward or extended without affecting the "successor activity" (not any other task or activity) and/or the Programme End Date.?
The other "Float" I may know is the "Total Float", all others, I have no idea how it works.
cheers!
Hi Guys,
I’ve had a bit of a dig around in the Planning Engineers Organisation - Glossary of Terms and they seem to have plenty of information there.
As a quick reference I’ve reproduced what I found here, but dont take it as definitive, I may have missed something.
Hope this is useful
Chris Oggham
Dear Mr.Greg,
Many Thanks for your valuable reply. I tried some problems with your explanations. hope i have got good result for the problems.Really good to learn some unknown terminologies from experienced persons like you...
Again telling thanks for the reply....
Regards,
S.Shaji
Shaji,
From my understanding there are 5 terms applied to float. In my experience only total and free float are used by planners.
There is Interfering float:- that is the difference in time between total and free float for that activity.
Independent float:-the difference between the earliest start time of earliest succeeding activity, less the latest activity start date of the selected preceding activity plus the duration. The independent float cannot be shared with any other activity.
These last two definitions were obtained from a construction planning text book - sorry cant remember which. I also remember the author said both were esoteric calculations and never used by planners.
Terminal Float; to my understand, is as Gary Whitehead explained it in his posting, but I don’t think it is yet recognised by PMBOK. I have found the Client PM uses this time to refute any builder claims for delay if the builder is ahead of time, and then delayed by the client. In this case the client claims to ‘own the float’. This is the only explanation I have been able to find that relates to float ownership that makes sense.
Hope this helps,
Greg
Hi Shaji,
Just related with Floats, there are two constraints available within P3, called ZERO TOTAL FLOAT and ZERO FREE FLOAT Constraint.
Zero total float constraint is used to make activity into critical whereas, zero free float constraint allows an activity to start as late as possible.
Cheers,
Mr. Gary
Thanks once again.... Interrupting Float is mentioned in our Planning planet wiki only under Planning Term---->Total Float. Pls check this...
Regards,
S.Shaji Mohamed
In some contract forms there is the concept of "Terminal Float". This is the difference between contractors forecast completion and contractualy mandated completion date, and is available for use solely by the contractor.
Though nto strictly float, there is also in some contracts a "Time Risk Allowance". This again is for use only by the contractor and is there to mitigate against possibility of overrun on activities with a high (schedule) risk.
If Stephen D sees this topic, Im sure hell give you a breakdown of "DRAG" which is not float but in the same ballpark.
Affraid Ive not come across "Interrupting Float" before.
Cheers,
G