SS and FF links do not work to build a hammock activity in MSP; you will have to use copye / special paste instead:
a) copy Bs start date and paste it with a link to As
b) copy Cs finish date and paste it with a link to As
3) add SS and FF links if you wish, but they are not necessary, they will only make you show the "purely logical" relationships between tasks, I mean they demonstrate relationships to the reader