Dear Thabeer,



Can you explain further ?



As I undrstood, even if you apply a filter P3 still sum up all resources (regardless of their unit) to compute budgeted quantity.



What I need is to get only the sum of manhours in the Budgeted quantity field.



Do i need to remove the other resource assignments (i.e. Material and Equipments) to achieve this ?



Please advice.