Hi Brian
To open a group of projects is independent from the data date. As far as I know the only impact would be for scheduling, float, longest path.
What you did was exactly what I suggested.
Regards
Dieter
Hi Dieter,
I am not 100% sure, but I believe that what I have done is the same as what you are suggesting me. Correct me if I am wrong
:)
I did indeed create a new EPS node (COMPLETE PROJECT.)
And under that node, Ive created 5 projects
Also, I would like to know if my sub-projects do not have the same data date, would I be able to open the EPS node? if yes, what would be my data date?
Regards,
Regards,
Brian
Hi Brian
This would lead to five projects. I would create an EPS-node and put them underneath.
Then youll have common access rights and the overall budget assigned on EPS-level. The common project would contain e.g. the contractual milestones, overhead activities, and e.g. a required shut-down. If youll open the EPS-node and all five have (exctly!, incl minutes) the same data date, P6 would regard and calculate them as one network/graph. Individual access rights and budget would be assigned to each project. Remark: Access rights are inherited from EPS to all projects and other nodes underneath.
Regards
Dieter
Hi Dieter,
My main reason for splitting into 4 projects is because they are practically independent and I want each of them to show their own critical path.
wouldn’t having them separated in WBS be the same as having them in different projects but under the same parent project? and opening the parent project?
-> COMPLETE PROJECT
----> GENERAL (anything that relates to all 4 sub projects)
----> SUB PROJECT 1
----> SUB PROJECT 2
----> SUB PROJECT 3
----> SUB PROJECT 4
by doing this, wouldn’t it also allow different data dates for each sub project? because they are all in the same project, I have to update all four of them at the same time.
Am I correct?
Regards,
Brian
Hi Brian
It depends on circumstances. Different projects if one of the following:
- Data exchange, e.g. with a sub for construction
- Subs have access to "your" P6 database to maintain their activities
- Need for independent scheduling
Easy way is within the view "WBS".
Good luck!
Dieter
To clarify my previous post. What I meant was:
I currently have 4 project in a P6 project separated by WBS and not EPS. I think that the latter method is a cleaner way of doing it.
Ill try to switch that (cutting and pasting)
Regards,
Brian
Hi Brian
If the software is under maintenance, youll get it free of charge from your dealer or from Primavera POINT (http://customerportal.primavera.com/customer). You can receive user id and password from Primavera. Theyll need your serial-no.
Regards
Dieter
May I suggest
Project Planning and Control Using Primavera P6 for All Industries Including Versions 4 to 6
By Eastwood Harris Pty Limited, Paul E Harris
Chapter 24 on Multiple Project Scheduling
http://books.google.com/books?id=jvul-jTSAAIC&pg=PT289&lpg=PT289&dq=HAN…
Hi Dieter,
if I use your definitions to describe my project, I would say that it is a program (big project consisting of 4 smaller projects) in one P6 project.
Where would I be able to find the update/patch?
Regards,
Brian
Brian
To avoid misunderstandings. A programme or big project can consist out of more single P6 projects - due to access rights, data exchange ... You can open them altogether or separately (=load into the memory"). Then P6 will regard it as one network (=graph) if the data date is the same.
P6 to P61 to P62 were just bugfixes and some improvements of small details. When you start the setup.exe, it will realize the old version and upgrade the database as well. Do not forget a backup.
P6.2 was the first release issued by Oracle and they announced to discontinue any bugfix for P6. Current version is P6.2.1.
Regards
Dieter
Hi Dieter,
How can I load each project seperately? I basically have 4 projects in one project.
when you suggest me to upgrade to 6.2, is it just a patch?
Regards,
Brian
Brian
I cant test it, but it sould work: Schedule the whole program, then unmark "ignore..." in the scheduling options, then load each project separately and schedule.
Another idea: make the data date different for each project - e.g. one hour difference. But Im not sure if it works.
Best solution: Upgrade to P6.2; its a bugfix as well.
Regards
Dieter
Hi Dieter,
Thanks in advance for your help.
But unfortunately, Im working with version 6.0
Regards,
Brian
Brian
If you have the actual version: P6.2, just try the following:
"F9" --> Options --> For: Calculate float based on finifh date of: mark "each project".
Hope this helps
Dieter