This is maybe boiling down to the way MS Project can produce data against the way another planning tool such as PowerProject. I must also consider my knowledge(or lack off) using MS Project, not used it in anger for a long time, have been using PowerProject.
The abreviations are
O/D - original duration
R/D - remaining duration
A/D - actual duration
e/s - early start
e/f - early finish
a/c - actual cost
r/c - remaining cost
If it cant be done using custom fields and formula then it cant be done. Will just have to hand ball it
Many thanks your replies, its good to get thoughts from others when drawings complete blank !
Before even thinking about the problem, or rather the more exotic and demanding version of the problem, the short answer is that maybe it is possible and maybe it isnt. Maybe it is easy and maybe it is hard.
But what is the point of spending time and effort trying to do something which is mainly cosmetic, and largely based on a whim, and adds not one $ of value, when the time and effort could be much better spent doing something which is more important and productive?
The Gantt Chart is primarily about Tasks, and all of the fields are Task fields. You could tag the Tasks manually as PM or Design and then group and sub-total on that, and then think about tagging with a formula
I can figure out what some of the abbreviations are, but can you tell me anyway, just to be sure.
On face value, it would appear MSP needs to produce 2 reports to do this, hence asking if via the use of custom fields and formula it was not possible to extract the cost information from the task for each reasource into the custom cost fields.
Actual Cost and Remaining Cost (of Resources) are Resource fields so the Actual Cost and Remaining Cost data is available for each Resource so the problem is only about extracting the data and arranging it.
If you "tag" each Resource with the department they are in by using a spare resource field, that is a text field, or the built-in Group field will do, then you will be able to sort, filter and group on that field.
fred, PM Department
bob, Design Services
carol, PM Department
ted, Design Services
alice, Design Services
Make a new Group (Project, Grouped By, More Groups etc) and group on the "tag" field.
Then in the Resource Sheet View, show the Cost Table, then run the Group that you just made
How about slightly re-phrasing the question so that we are asking to see:
Actual Cost For Tasks with PM Group resources assigned.
Remaining Cost for Tasks with PM Group resources assigned.
In the Gantt Chart View, and showing the Cost Table, Group by Resource Name.
This is not one of the built-in Groups so you will have to make one (Project, Group By, More Groups)
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
Trevor
Totally agree with your first 2 paragraphs.
This is maybe boiling down to the way MS Project can produce data against the way another planning tool such as PowerProject. I must also consider my knowledge(or lack off) using MS Project, not used it in anger for a long time, have been using PowerProject.
The abreviations are
O/D - original duration
R/D - remaining duration
A/D - actual duration
e/s - early start
e/f - early finish
a/c - actual cost
r/c - remaining cost
If it cant be done using custom fields and formula then it cant be done. Will just have to hand ball it
Many thanks your replies, its good to get thoughts from others when drawings complete blank !
Cheers
Before even thinking about the problem, or rather the more exotic and demanding version of the problem, the short answer is that maybe it is possible and maybe it isnt. Maybe it is easy and maybe it is hard.
But what is the point of spending time and effort trying to do something which is mainly cosmetic, and largely based on a whim, and adds not one $ of value, when the time and effort could be much better spent doing something which is more important and productive?
The Gantt Chart is primarily about Tasks, and all of the fields are Task fields. You could tag the Tasks manually as PM or Design and then group and sub-total on that, and then think about tagging with a formula
I can figure out what some of the abbreviations are, but can you tell me anyway, just to be sure.
Trevor
Thanks for the reply. A possible solution that I will need to put forward.
Basically the client had seen some example reports done in PowerProject. One of which showed the gantt chart and the spreadsheet side detailing
ID, Name, O/D, E/S, A/D, R/D, E/F, E/F Variance, A/C PM Services, R/C PM Services, A/C Design Services, R/C Design Services.
On face value, it would appear MSP needs to produce 2 reports to do this, hence asking if via the use of custom fields and formula it was not possible to extract the cost information from the task for each reasource into the custom cost fields.
Actual Cost and Remaining Cost (of Resources) are Resource fields so the Actual Cost and Remaining Cost data is available for each Resource so the problem is only about extracting the data and arranging it.
If you "tag" each Resource with the department they are in by using a spare resource field, that is a text field, or the built-in Group field will do, then you will be able to sort, filter and group on that field.
fred, PM Department
bob, Design Services
carol, PM Department
ted, Design Services
alice, Design Services
Make a new Group (Project, Grouped By, More Groups etc) and group on the "tag" field.
Then in the Resource Sheet View, show the Cost Table, then run the Group that you just made
How about slightly re-phrasing the question so that we are asking to see:
Actual Cost For Tasks with PM Group resources assigned.
Remaining Cost for Tasks with PM Group resources assigned.
In the Gantt Chart View, and showing the Cost Table, Group by Resource Name.
This is not one of the built-in Groups so you will have to make one (Project, Group By, More Groups)