can I put RD > OD in P3 !
Forum Sponsor
Top Posters
Josephus Enot
1 posts
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
thanks really
Mimoune yâ khô,
P3 computes Pct to be equal to (OD-RD)/OD and not under 0; therefore, when you enter RD > OD, Pct becomes 0; should you have OD = 3, RD = 4, "new scheduled duration" = 7, you will enter Pct accordingly
Have a good time in Arzew, I am going back to Paris and be in Algiers again within one month inchallah
Alexandre
escander yeah my friend, i am always in arzew, now it become very interesting, many nationalities, we lack only people from Antarctica.
Joao Reibero, yes of course, this option is off, otherwise i cant get P3 to show me, RD> OD
Please can you take a look at this thread and tell me what you think !!
http://www.planningplanet.com/forum/forum_post.asp?fid=&Cat=1&Top=58911…
thanks very much
Have you checked the options "Link remainig duration and schedule percent complete" and the ones for summarization?
HTH
saha mimoune, ouash rak?
I just faced the same situation today while giving a training session on P3 in Hydra
I have entered the total percent complete by hand in the Pct field
is Arzew still fine for you?
Alexandre iskander el dziri