in the pop-up menu, click the 6th option from top, should be "Hide column"? Sorry for "Mask", I am using MS Project in French, and I am afraid my translation was not accurate.
MS Project is using the same words as MS Excel; be advised that, to display the column again, you will have to "Insert a column", then to select the field in the drop down list
Sorry for my previous mistake and your misunderstanding
Although MS Project is not my software of choice, ocassionally I had to deal with it. Let’s see if I can be of help.
After you cost &/or resource load your activities:
-go to the Resource Graph and right click on the right side of the graph and select Cummulative Cost / Cummulative Work.
-Then click Bar Styles and select Show as Line for Filtered Resources and Resource selection boxes.
-You will get s-curve based on early dates
For s-curve based on late dates
-Create a new job file from original.
-Set all tasks to as late as possible constraint.
-Update project.
-Verify no re-scheduled task overrides any finish no latter than constraint you previously had in the original. If so re-set those to your original finish no latter than constraint.
it is not possible to produce a S curve with MS Project by itself; if you are using MS Project 2003 or lower, you will have to use the "Export timescaled data to Excel" functionnality; if you are using MS Project 2007, you will use Visual Reports
in both cases, select the "Cumulative work" and "Cumulative Cost" fields
to delete a column from a view, right clic on the column name, then Mask column
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
That was why I was intrigued. Thanks though sir ALEXANDRE. You have been so generous to members. Keep posting, sir.
_______________
Fereson
Mohnish,
In MS Project to display the column again, right clic the column name of the column BEFORE which you want to insert back the hidden column,
then clic "Insert a column",
and select the field in the drop down list
Alexandre
Alexandre Sir,
When we hide the column in MS excel the same hidden column can be regenerated by using unhide option.So is that possible in MS project also.
Sir Thanks a lot hiding column is working for me in MSP.
Regards
Mohnish
Mohnish and Fereson,
To delete a column from the current view,
right clic thne column name (say: Predecessor)
in the pop-up menu, click the 6th option from top, should be "Hide column"? Sorry for "Mask", I am using MS Project in French, and I am afraid my translation was not accurate.
MS Project is using the same words as MS Excel; be advised that, to display the column again, you will have to "Insert a column", then to select the field in the drop down list
Sorry for my previous mistake and your misunderstanding
Alexandre
Alexandre Sir,
I am using MSP-2003.I tried right clicking the cloumn to delete but didntt find "mask column" option.
Please help me out over this.
Thanks and Regards
Mohnish
Sir Alexander,
I tried right clicking a column to delete but then I didnt find any "Mask Column" option.
Thanks,
Fereson
Mohnish
Although MS Project is not my software of choice, ocassionally I had to deal with it. Let’s see if I can be of help.
After you cost &/or resource load your activities:
-go to the Resource Graph and right click on the right side of the graph and select Cummulative Cost / Cummulative Work.
-Then click Bar Styles and select Show as Line for Filtered Resources and Resource selection boxes.
-You will get s-curve based on early dates
For s-curve based on late dates
-Create a new job file from original.
-Set all tasks to as late as possible constraint.
-Update project.
-Verify no re-scheduled task overrides any finish no latter than constraint you previously had in the original. If so re-set those to your original finish no latter than constraint.
-Update project.
Hello Mohnish,
it is not possible to produce a S curve with MS Project by itself; if you are using MS Project 2003 or lower, you will have to use the "Export timescaled data to Excel" functionnality; if you are using MS Project 2007, you will use Visual Reports
in both cases, select the "Cumulative work" and "Cumulative Cost" fields
to delete a column from a view, right clic on the column name, then Mask column
Hope this helps,
Alexandre