Import Excel, not taking in the Original Duration...
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Tim,
You need to cite an example in order to easily understand what you need.
Anyway, the default of duration type is "Fixed Duration & Units whenever you create a new a project. This is only applicable when you create or add new activities.
Regards.
OK, so no one replied and I figured it out on my own.
Just in case anyone cares, You have to go to the Defaults tab for the given project you are importing to and change the Duration Type to Fixed Duration & Units.