Importing progress percentage not working
Forum Sponsor
Top Posters
Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts
Hi Hady,
Equal or not equal, still you have to filter or use the "If Paramaters" if you are going to use the global change.
The easiest way is to show the % complete type on the column.
Regards.
Hi Arnold
your method may enough if the % were equals.
Regards
Hi Hady,
Even without utilizing the global change, you can easily change the % complete type by showing them into column and use the command fill down.
Regards.
try to create user field, when export to excel be sure to add that field
in excel use it as your % completion
in P6 use globel change to convert that field to Duration or Physical duration.
Regards
Hi,
I dont think so...
Wow
you think that with the new version they improve and make the planners life easier instead ...
May be in PM7 the opportunity will be back
L
Hi Luca,
Yes, I have tried all the PCT fields in P6 and export to Excel. All of them having the (*) next to column title.
Have a nice day too.
Regards,
Arnold
Hi
did you try to export all PCT fields and see which one has not the * near by?
Is how I have done to find out which one I could use for my update
Sorry for the missunderstanding on PM5-PM6.
Have a nice day
Luca
Hi Luca,
I forgot about PM5 but if you have done and it works for you then its fine. However, in P6 it doesnt work. Anyway, thanks for the info.
Regards,
Arnold
Hi
I just done a progress update on PM5 this morning, using "Activity % Complete(%)" and worked
May be in PM6.2 this field is not locked
L
Hi Luca,
You just mentioned the asterisks (*) in the heading cannot be imported. However, "Activity % Complete" also has.
How can you export back to P6? Can you tell us?
Regards,
Arnold
Hi
from excel you have to import back the "Actvity % Complete"
All other PCTs that have an * near the headings are not importable back in Primavera Enterprise
L
Hi Kier,
You need to change your remaining duration: Because Duration % Complete equals to (OD - RD)/OD*100.
Where: OD is taken from the current plan & not from the baseline.
HTH.
Arnold
Duration % complete probabaly not a field that is importable. Any field that has an asterisks in the heading cannot be imported.