Resource Usage Profile Cummulative Curves

B
Brian Yung 👤 Member for 17 years 3 months
A
Arnold Puy 👤 Member for 19 years 1 month

Hi Brian,



The reason why your Budgeted Units (Budgeted Bars) moves it is because, some of the activities already in progress and completed. These activities use the budgeted values with planned dates.



It is also happened when at complete duration is greater than original duration. Try to notice, for those activities still not yet started. Budgeted Units equals to remaining early units.



With regards to your query on how to fix this, save a copy of your current schedule and assign this as your baseline then go to Admin  Admin Preferences  Earned Value Tab, under “Earned Value Calculation” select the “Budgeted values with current dates” then press (F9) or schedule your project.



The other workaround is to create global change, making that

“Planned Start/Finish” equal “Start/Finish” but you need to have the “if condition” that,



“Activity Status” is not equal “Not Started”

“Activity Type” equals “Task Dependent” (If you have milestone in your programme)



This is to avoid error message during running the global change.



Hope this helps.



Regards,



Arnold

M
Michael Ridino 👤 Member for 17 years 1 month

I think I had the same problem on an past schedule. The resources get calculated using the planned start and finish, which can be different from the normal start and finish. Put in columns for planned start and finish as well as start as finish for the activities and see if they match.



If they are different, manually change the planned dates to match and hopefully your curve will be correct.



Mike

Forum Sponsor

Top Posters

Nick Johnson-Pond
3 posts
sairedz25
0 posts
Ahmed Awad
2 posts
Syed Shoeb
0 posts
Vimukthi
0 posts
bal aji
2 posts
Lee Mallek
23 posts
Viet Tran
9 posts
Ola Gbotoso
0 posts
Jaturapit Multongka
1 posts