Changing Fixed Units to Fixed Duration
Forum Sponsor
Top Posters
Julian Pegg
1 posts
Peter Nagy
2 posts
Raymund de Laza
17 posts
Syed_Asad
0 posts
Tony Greyvenstein
0 posts
Ahmed Al-Jubouri
13 posts
Umar Alvi
3 posts
Sibusiso Mahlalela
0 posts
Michael Samanyayi
3 posts
Simon Gumede
0 posts
Have you tried just selecting Tasks and using Task Information, Advanced?
Whats wrong with the way it is, or what is the reason for wanting to change it?
Since there are no resources assigned and no assignments being made, the Task Type and Effort Driven settings have no effect and make no difference and the % Complete and Finish Dates will not change.
Fixed Units and Effort Driven ON are the MSP defaults so it is no surprise that thats how you get them.