Changing Fixed Units to Fixed Duration

T
Trevor Rabey 👤 Member for 20 years 6 months

Have you tried just selecting Tasks and using Task Information, Advanced?

What’s wrong with the way it is, or what is the reason for wanting to change it?

Since there are no resources assigned and no assignments being made, the Task Type and Effort Driven settings have no effect and make no difference and the % Complete and Finish Dates will not change.



Fixed Units and Effort Driven ON are the MSP defaults so it is no surprise that that’s how you get them.