Paul Smith 👤 Member for 19 years 5 months
P
Paul Smith 👤 Member for 19 years 5 months

Sorry Guys, I figured it out for myself.



The PM had been in and statused these milestones as x% complete of course this is wrong, milestones are either zero or 100%). MSP saw this to indicate a change of type to an activity (which can be x% complete) and slits it as it reschedules the finish date.

I will be aware of this and test for it before doing this again.