Page breaks in reports

M
Mark Heard 👤 Member for 22 years 2 months
A
Alexandre Faulx-Briole 👤 Member for 23 years 4 months

There is no pagebreak functionality in MSP reports, whatever MSP version you are using.

Try replacing a report by the equivalent View, for instance "Task list" view instead of the "Task" report, ...

Use Insert, Pagebreak to break between two rows.

Alexandre

D
Dayanidhi Dhandapany 👤 Member for 23 years 2 months

I believe there is no such facility available in MS Project 2000, either you have to insert page break manually in task sheet view or write some customised programme in VBA / Macro for MS Project.