hi,it is already defined and exist in the activity code..
if in the project #1:i have level 1 and level 2
and in the project # 2:i have level 3 and level 4.
i put in the group and sort the 4 levels,but when i open the both project:in the first project:it is defined level 1 and level 2(no problem),and is written in the first project no level 3,level 4.
and in the project 2:it is ok for its level but also is written :no level 1,no level 2.
Spider Project is most functional and powerful professional project management software.
The first SP version was launched in 1993 and since then it has been constantly improved. Today is used in 34 countries though most Spider Project customers are in Russia. Spider Project offers numerous unique functional features and is the only PM software that optimizes resource, cost, and material constrained schedules and budgets for projects and portfolios.
The unique features of Spider Project include Quantity Based Scheduling, Conditional Scheduling, Skill Scheduling, Optimal Resource, Cost and Material Leveling, Resource Critical Path Calculation, Cash and Material Flows Calculation and Management, Trend Analysis, Advanced Risk Simulation and Analysis, Calculation of Success Probability Trends, Calculation and Management of required Project Time and Cost Buffers, Application of Corporate Norms, Management of many Parallel Budgets, Multiple WBS and many others.
Spider Project was and is used for management of many large scale programs in Russia, including $51bln construction program for 2014 Winter Olympic Games preparation.
The application areas where Spider Project is successfully used include Aerospace, Banking, Construction, Defense, Energy, Engineering, Infrastructure, Manufacturing, Metallurgy, Mining, Oil & Gas, Railways, Retail, Shipbuilding, Software Development, Telecommunications, Utilities, etc.
P6-Auditor - Display information from Primavera P6 audit tables in a user-friendly format
Unifier-Archiver - Extract and archive important documents and attachments from Primavera Unifier
Unifier-Loader - Load data into and out of Unifier via Excel
PCM-Loader - Import data into Primavera Contract Management with flexible and secure, template-driven Excel spreadsheets
PCM-Archiver - Extract and archive important documents and attachments from Primavera Contract Management
PCM-Unifier Migrator - Automatically transfer live and historical data from Primavera Contract Management to Primavera Unifier with ease
Create Radically Better Construction Schedules with ALICE Technologies
Use the power of AI to create construction schedules that reduce risk while cutting costs and build time. With ALICE, develop the ideal schedule during preconstruction -- or recover projects that are off schedule and over budget.
i do agree with this proposal
Roger,
Create a global code with all values that might be used in both projects...
and then assign this new global code to activities in both projects
your code might be : Building Level with four values: 1,2,3,and4
and then using global change (to speed things up) assign your new code to the activities and organize using the new code not the old one
remember to check the "hide if empty" to avoid empty groups
it is not a problem of "hide..."
the problem as i told in the project 1 we have level 1,level 2 and in the project 2:level 3,and level 4
the problem is:if i activity concrete for example in the project 1,look what it will give me:
level 1(project 1)
level 2(project 1)
no level 3(project 2)
no level 4(project 2)
concrete
i dont want to appear in the project 1 the "no level 3 and no level 4 foe project 2"
THANKS
Not quite sure what you mean but do you want to hide the no level, if you do just tick Hide If Empty in the Group & Sort view
hi,it is already defined and exist in the activity code..
if in the project #1:i have level 1 and level 2
and in the project # 2:i have level 3 and level 4.
i put in the group and sort the 4 levels,but when i open the both project:in the first project:it is defined level 1 and level 2(no problem),and is written in the first project no level 3,level 4.
and in the project 2:it is ok for its level but also is written :no level 1,no level 2.
I hope u understand my sequences.
thanks a lot
maybe you need to define your codes as similar as you can with all your projects.