Current Project finish date And Baseline finish are sa

Member for

17 years 5 months

Gents



Please look at the following thread;

http://www.planningplanet.com/forum/forum_post.asp?fid=1&Cat=9&Top=48465



Particularly & I quote from David’s post;

"Also, a point to anyone who wishes to supply printed material (all be it scanned), what is the copyright of the document?



On this forum we have fantastically intelligent people who make a living from publishing great books and guides that we all use, by scanning and copying we are depriving that author of their rightful payment.



So, if you are not the author or rightful owner of the works or you do not have the specific permission of that entity to copy their works, please do not do it.



We will not condone copyright theft."



Regards

Mark

Member for

17 years 8 months



Thanks , Mr Puy.



My explanation was not clear ..it was my main problem.



again Thanks.



I would like share my Training Manual which is full of example solving prob..etc..





Thanks so much for Your advice.



Regards

Shahzad

Member for

17 years 8 months



Hi Mr. Puy



i create a copy of my master Schedule before update that



Basline -B1 which listed in my based Maintain base line Tab.



Ans. of your question yes i know how to save a copy thru Maintain basline / restored etc.



my problem has been solved with my training Manual.



In the manual

Member for

18 years 6 months

Hi Shahzad,



If I understood you, your project & primary baseline is your current schedule. Therefore, your current & baseline schedule are the same.



Your current programme should came from the baseline programme and being updated weekly or monthly depending on your contract requirements.



My question is, do you know how to maintain & assign baseline? If not, then here are the steps:



1. Create a copy of your Approved Baseline Programme.

2. After creating, go to Project Menu --> Maintain Baseline then select "ADD".

3. Tick the "Convert another project to a new baseline of the current project" then OK.

4. Select the newly created copy of your Approved Baseline and assign & close.

5. Go to Project Menu --> Assign Baselines, and assign the added Approved Baseline to "Project or primary baseline".



Hope this helps.



Regards,



Arnold

Member for

17 years 8 months

first time i had perform the step.



Project Name Overrall





Maintain a Basleine as a Overall-B2



Then Baseline assign as Follows.



Project



Overall



PROJECT Basline



overall-B2



User baseline

PRIMARY



Overall-B2



The above step is also not worrking.



Thnaks

Member for

17 years 8 months

Project name is Overall



1.I have maintain a base Line as a Overall-2



2. Assign baseline as:



PROJECT

(overall)



PROJECT BASELINE

(current Project)



USER BASELINE

PRIMARY

(current-project)



hope find the solution.



Thanks